# ADR-0005: MVP Release Artifact and Release Gates

- **Status**: Accepted
- **Date**: 2026-04-22
- **Authors**: Bellona Remote Control Working Group, Codex
- **Reviewers**: Bellona, Psyche, Yemaya, Oshun Platform, Oshun Security

## Context and Problem Statement

Phase 180 uses several gate names: MVP, Alpha Hardening, stable release, final
verification, and GA-style final release. The checklist now labels `180.C.16` as
`Alpha Hardening and MVP Release Gate`, while `180.C.29` is
`Final Verification, Documentation, SDKs, and Release`. Some older wording still
says that `180.C.16.09` gates a "stable release", which conflicts with the later
final verification and acceptance tasks in `180.C.29.08`-`.10`.

Without a single release-artifact definition, future agents can accidentally
ship too little at MVP, overblock MVP on production-stage work, or treat the
final release gate as redundant. This ADR defines what the Phase 180 MVP
artifact is, which stages must be complete for it, which demo scenarios must
pass, which documentation ships, and how the Stage 16 and Stage 29 gates relate.

## Decision Drivers

- Keep the first usable release focused on the macOS-first remote creative
  control path chosen in ADR-0004.
- Require enough policy, approval, audit, timeline, and hardware evidence before
  mutating remote creative tools are considered MVP-ready.
- Avoid blocking MVP on production coverage stages that intentionally come after
  the MVP, such as Blender production commands, browser production automation,
  Control Room production experience, Unreal production coverage, fleet
  expansion, and Windows/Linux host parity.
- Preserve a stronger final gate for GA/releasable production use.
- Make demo scenarios concrete enough that release evidence cannot be
  hand-waved.

## Considered Options

### Option 1: Treat `180.C.16` as the Final Stable Release Gate

The first hardening gate would ship the stable product and make later production
coverage stages optional enhancements.

This option is rejected. It contradicts the ordering of production Blender,
browser, Control Room, Unreal, networking, packaging, security, operations, SDK,
and final acceptance stages that follow `180.C.16`.

### Option 2: Treat `180.C.29` as the Only Release Gate

MVP language before Stage 29 would be treated as development scaffolding, and no
MVP artifact would ship until final verification.

This option is rejected. It would remove the product value of the Phase 180 MVP
stages and delay feedback on the control plane until after broad production
coverage work.

### Option 3: Two Explicit Gates: MVP Alpha at `180.C.16`, Final GA at `180.C.29`

Stage 16 ships a controlled, macOS-first MVP alpha artifact. Stage 29 ships the
final GA/releasable artifact after production coverage, documentation, SDKs,
hardware evidence, security, operations, and acceptance scenarios are complete.

This option is chosen.

## Decision Outcome

Bellona adopts a two-gate release model:

1. **MVP Alpha Artifact Gate (`180.C.16`)**: a macOS-first, operator-supervised,
   policy-gated release artifact suitable for internal dogfooding and tightly
   controlled pilot use. It proves the architecture end to end on the MVP path.
2. **Final GA Artifact Gate (`180.C.29`)**: a documented, SDK-accessible,
   operator-usable, production-release candidate after production command
   coverage, hardening, evidence, deployment, security, and acceptance work.

`180.C.16.09` is interpreted as the **MVP alpha release gate**, not the final
stable/GA gate. `180.C.29.08`-`.10` remain the final verification, release
evidence, and product acceptance gate.

## MVP Alpha Artifact

The MVP alpha artifact ships as a versioned source commit plus reproducible
local builds and deployment instructions for:

- `libs/bellona/remote-protocol` generated contracts and schema ownership docs.
- `apps/bellona/remote-gateway` with durable-enough MVP storage, device/session
  lifecycle, command routing, policy, approval, audit, timeline, and local/cloud
  deployment smoke paths.
- `apps/bellona/remote-host` for macOS-first controlled-host operation with
  development-to-production credential migration path and host outbound
  connection.
- Bellona Control Room MVP for device list, session timeline, approvals,
  screenshot/stream placeholder, pause/stop, and operator workflow.
- MCP/cloud-agent MVP tools that cannot bypass gateway policy, approvals,
  revocation, command schemas, or audit.
- Blender read-only scene info and safe primitive creation through the remote
  path with audit, approval where required, rollback/undo notes, and evidence.
- Browser managed-profile launch, navigation, snapshot, screenshot, and cleanup
  through localhost-only host automation.
- Desktop fallback MVP for explicitly allowlisted macOS screenshot/window/focus
  and click behavior with permission diagnostics and visual verification.
- Unreal MVP for project/world read-only query and first safe actor spawn using
  the same policy, audit, evidence, and approval path.
- Audit/timeline export sufficient for the MVP scenarios.
- Release evidence bundle linked from the implementation tracker.

The MVP alpha artifact is **not** a broad production automation release. It does
not require Windows or Linux hosts, Tier-2 DCC adapters, production Blender
command coverage, production browser automation, full Control Room production
experience, fleet scheduling, GA SDK parity, or old-bridge removal.

## Stages Required for MVP Alpha

The MVP alpha gate requires these stages complete:

- `180.C.01` Phase control and ground rules.
- `180.C.02` audit notes, ADRs, compatibility, trust, hardware, and MVP artifact
  decisions.
- `180.C.03` protocol package and contract drift checks, including added pre-MVP
  protocol refinements if they are needed by security gates.
- `180.C.04` mock harness and contract tests.
- `180.C.05` remote gateway walking skeleton and command routing.
- `180.C.06` remote host walking skeleton.
- `180.C.07` pairing, auth, policy, approvals, and audit coverage.
- `180.C.08` audit, observability, timeline, artifact metadata, redaction,
  logging, metrics, and audit-failure behavior.
- `180.C.09` Blender read-only adapter MVP.
- `180.C.10` Blender safe mutation MVP.
- `180.C.11` browser CDP MVP.
- `180.C.12` live stream and minimal Control Room MVP, with screenshot-only mode
  accepted before full WebRTC if documented.
- `180.C.13` desktop fallback MVP.
- `180.C.14` MCP and cloud-agent MVP.
- `180.C.15` Unreal read-only and safe mutation MVP.
- `180.C.16` alpha hardening and MVP release gate.

Items added after Stage 16 may be started later but are not MVP alpha blockers
unless a later ADR explicitly promotes them.

## MVP Alpha Demo Scenarios

All MVP alpha demo scenarios must pass and produce release evidence:

| Scenario ID | Scenario                                                                  | Required Rigs / Modes                                     | Evidence                                                                                                 |
| ----------- | ------------------------------------------------------------------------- | --------------------------------------------------------- | -------------------------------------------------------------------------------------------------------- |
| `MVP-01`    | Pair two Macs on same LAN, start a session, list device capabilities.     | `MAC-OP-01`, `MAC-HOST-01`, same-LAN gateway              | Pairing audit entry, device registry state, session timeline, capability report.                         |
| `MVP-02`    | Query Blender scene info through gateway -> host -> adapter.              | `MAC-HOST-01`, Blender baseline                           | Scene-info result, adapter health, audit/timeline entries, fixture scene version.                        |
| `MVP-03`    | Create one Blender primitive with policy, approval if required, and undo. | `MAC-HOST-01`, Blender baseline                           | Approval decision, before/after scene info, undo checkpoint, audit entries, rollback note.               |
| `MVP-04`    | Launch isolated browser, navigate, snapshot, screenshot, and close.       | `MAC-HOST-01`, Chrome for Testing or Playwright Chromium  | Browser profile path, CDP localhost proof, screenshot artifact, audit/timeline entries.                  |
| `MVP-05`    | Use desktop fallback against an allowlisted macOS window.                 | `MAC-HOST-01`, Screen Recording and Accessibility granted | Permission report, window list/focus, screenshot, visual click verification, audit/timeline entries.     |
| `MVP-06`    | Operator approves, denies, pauses/stops, and replays a session.           | `MAC-OP-01`, Control Room MVP                             | Control Room test output, approval records, pause/stop events, replay/export artifact.                   |
| `MVP-07`    | Cloud-agent smoke flow through one reference cloud gateway.               | `MAC-HOST-01`, one cloud rig, optional TURN placeholder   | Device list, session start, Blender query, browser screenshot, session stop, gateway logs, audit export. |
| `MVP-08`    | Unreal MVP read-only query and first safe actor spawn.                    | `MAC-HOST-01`, Unreal baseline                            | Project/world query, spawn result, policy/audit/evidence, timeout/cancel behavior where applicable.      |
| `MVP-09`    | Revoked host and denied policy cannot execute commands.                   | `MAC-HOST-01`, gateway tests and local smoke              | Revocation result, denied command result, no host dispatch, audit entries.                               |
| `MVP-10`    | Network impairment smoke for reconnect and degraded mode.                 | `NET-IMPAIR-01`, same-LAN or cloud gateway                | Packet-loss/high-latency run, host reconnect, command timeout/degraded state, audit continuity.          |

## Documentation Shipped at MVP Alpha

The MVP alpha docs bundle must include:

- Architecture overview for topology, trust boundaries, gateway authority, host
  enforcement, protocol ownership, adapter boundaries, and MCP/Control Room
  client roles.
- Operator runbook for two-MacBook LAN setup, cloud gateway setup, pairing,
  permissions, approvals, pause/stop/takeover, replay/export, revocation, and
  uninstall.
- Developer guide for adding commands, adapters, policy rules, approval gates,
  audit evidence, and tests.
- Hardware rig inventory and compatibility matrix.
- Security/trust docs covering prompt injection, browser profile isolation,
  desktop fallback limits, path grants, revocation, redaction, and audit
  retention.
- Troubleshooting runbooks for permissions, plugin repair, stream failure,
  gateway restart, host reconnect, audit export, update rollback, and diagnostic
  bundles.
- Known limitations and explicit non-MVP surfaces: Windows/Linux hosts, real
  browser profiles, arbitrary shell, arbitrary Blender Python, Unreal console,
  production browser automation, full fleet scheduling, Tier-2 DCC adapters, and
  old bridge removal.

## Final GA Gate

The final GA artifact remains governed by `180.C.29.08`-`.10` and requires the
broader checklist to be complete or explicitly blocked with an accepted waiver.
It includes:

- Production Blender command coverage (`180.C.17`, `180.C.18`).
- Browser production automation and optional external browser-agent decisions
  (`180.C.19`, `180.C.20`).
- Control Room production experience (`180.C.21`).
- File/artifact/cross-app workflow coverage (`180.C.22`).
- Unreal production command, Sequencer, render, build, and diagnostics coverage
  (`180.C.23`, `180.C.24`).
- Networking, cloud deployment, transport, and streaming hardening (`180.C.25`).
- macOS packaging, permissions, signing, updates, diagnostics, SBOM, and
  cross-platform abstraction docs (`180.C.26`).
- Security, privacy, governance, observability, replay, SDK, CLI, final docs,
  release evidence, and acceptance (`180.C.27`-`180.C.29`).

Windows and Linux host stages (`180.C.36`, `180.C.37`) are Phase 180 expansion
work per ADR-0004. They are not MVP alpha blockers. A final GA release may ship
without Windows/Linux only if the release notes explicitly scope GA to macOS
hosts and `180.C.36`/`180.C.37` remain unchecked or blocked with an accepted
scope waiver.

## Normative Rules

- Do not call the Stage 16 artifact stable or GA.
- Do not check `180.C.16.09` unless all MVP alpha required stages, demo
  scenarios, docs, verification, and evidence are complete.
- Do not check `180.C.29.08`-`.10` based only on MVP alpha evidence.
- Every MVP demo scenario must include automated test output where possible and
  hardware/manual evidence where the hardware inventory says CI is insufficient.
- Any missing MVP demo scenario must block MVP alpha unless an accepted ADR
  changes the MVP scope.
- Future final release notes must clearly state whether the release is MVP
  alpha, macOS GA, or cross-platform GA.

## Acceptance Criteria

- This ADR exists under `docs/domains/bellona/extras/remote-control/adr/`.
- The decision defines the MVP alpha artifact and final GA artifact separately.
- The ADR lists stages required for MVP alpha.
- The ADR lists MVP demo scenarios and documentation shipped at MVP alpha.
- The ADR resolves the `180.C.16.09` versus `180.C.29.08`-`.10` ambiguity.
- The tracker row and Phase 180 checklist item for `180.C.02.16` are updated.
- Markdown formatting verification passes for this ADR, the tracker, and the
  phase checklist.

## Consequences

Positive consequences:

- Future agents have one source of truth for what MVP alpha means.
- Stage 16 can produce real feedback without pretending production coverage is
  done.
- Stage 29 retains its stronger final verification role.
- Demo scenarios give release evidence concrete shape.

Negative consequences:

- Some checklist text and future rows must honor the new alpha/GA distinction.
- The MVP remains a controlled pilot artifact, not a broad customer release.
- Final GA may still require scope decisions if Windows/Linux remain incomplete.

## Related Decisions

- `docs/domains/bellona/extras/remote-control/adr/ADR-0001-standalone-remote-gateway-and-host.md`
- `docs/domains/bellona/extras/remote-control/adr/ADR-0002-remote-control-threat-model.md`
- `docs/domains/bellona/extras/remote-control/adr/ADR-0003-gateway-trust-and-e2e-encryption-model.md`
- `docs/domains/bellona/extras/remote-control/adr/ADR-0004-cross-platform-remote-host-scope.md`
- `docs/domains/bellona/extras/remote-control/compatibility-matrix.md`
- `docs/domains/bellona/extras/remote-control/hardware-rig-inventory.md`
- Future `180.C.16.09` and `180.C.16.11` release-gate implementation.
- Future `180.C.29.08`-`.10` final verification and acceptance.

## References

- `TODOS/phase-180.md`
- `TODOS/phase-180-gaps.md`
- `docs/domains/bellona/extras/remote-control/implementation-tracker.md`